GMOS-S update
GMOS was installed on the telescope, but it is not available yet due to the issue with CCD2 on the GMOS detector array, which features enhanced noise structure. The troubleshooting will be carried away during this week.
GMOS was installed on the telescope, but it is not available yet due to the issue with CCD2 on the GMOS detector array, which features enhanced noise structure. The troubleshooting will be carried away during this week.
Zorro will be removed on Sept 1st for its optics realignment between Sept 8 to 10th. It will be installed back on the telescope between Sept 13 and 15th, and be ready before the Zorro run starting on the 16th.
UPDATE (Sep 03): the repair work will extend through mid-September. The reason for this is that one of the optical components of the OI probe needs to be re-attached to the pickoff arm after it was found loose. The work will also involve the corresponding optical alignment check.
Due to a mechanical failure, The GMOS-S OIWFS will be out of service at least for the rest of August. A repair plan at the CPO Instrument Lab is being worked on. As a consequence of this situation, GMOS-S will be available only with PWFS2 as guiding option.
The Zorro blue filter wheel, that had been faulty since last March, was successfully replaced last week. An unfortunate side-effect of the procedure is that the red and blue cameras are now misaligned by about 6 arcsecods, a shift bigger than the speckle field-of-view, which makes simultaneous observations with both cameras in speckle mode impossible. Both cameras are working fine, only independently. New PIs should therefore indicate which camera they want to use. Both cameras can still be used, but this will imply doubling the requested time.
It was recently reported that the observed counts in spectra seemed to be lower than expected on CCD1 for some programs - also, odd emission-like features (‘spikes’) were noticed in the CCD1 portion on stellar spectra that are known to be featureless. All this applies only to data acquired during the ‘bad-CTE’ periods of CCD1, i.e. between:
NIFS has a cryogenic issue which started at the time of the earthquake and power outage on Monday 5th July. This problem has developed and it is now clear that the instrument must be warmed up completely to effect mitigation. NIFS will remain off the telescope until this is completed; NIRI will remain on for the time being.
The GHOST project continues to be on hold due to the pandemic and we do not expect to start the re-assembly and test of the instrument at Cerro Pachon this year. We are hopeful that the travel restrictions will ease in the first half of 2022 so this work can begin. In the meantime, we continue to make incremental improvements to our software and documentation, and order spare parts.
After a minor fix to its controlling computer, Zorro is back online starting May 31.
April 24th, 2022: GNIRS will be removed from the telescope on April 28th, 2022 and is planned to be unavailable for use until July 6th, 2022 due to the GNIRS IFU installation and refurbishment projects.
May 17th, 2021: The GNIRS IFU installation, originally planned for 2021B, has been postponed until 2022. Therefore, GNIRS will be available for the entire 2021B semester.
After overcoming an issue with the compressors and another with the temperature in the MOS dewar, F2 has been back to queue operations since April 23rd.