[Mayan calendar]

Director's Discretionary Time Summary : Semester 2015A GN

The data shown in the tables below summarise the programs that constitute the "Director's Discretionary Time" (DDT) on GN. DDT proposals are typically for time-critical observations which cannot wait for the normal proposal cycle (e.g. unexpected astronomical events) or for testing the feasibility of a technique or of a program. See the DDT web page for more information. DDT proposals may be submitted at any time by any astronomer world-wide.

In other respects - contact scientist support, Phase II definitions, Gemini Science Archive data distribution - DDT programs are similar to other Gemini queue programs.

This report is generated daily (see the bottom of the page for the current timestamp). The pages linked via Execution Status are updated approximately every 4 hours. Note that the completion fraction may change as the time accounting is adjusted during the quality assessment process.


The columns in the table for Gemini North are:
Ref # Gemini reference number (note that this is different from any internal National TAC reference number). Click on it to see the proposal abstract (when available).
PI Name of Principal Investigator. (If a joint proposal, the name of the primary contact for the entire program is listed).
Partner Partner (UH = University of Hawaii, GS=Gemini staff) or country (US, UK, CA, CL, AU, AR, BR) to which time will be charged. If a joint proposal, all contributors are shown.
Title The title of the science program.
Instrument Name of the instrument(s) required.
Hours Allocated Time allocated to the program (if a joint proposal, this is the total time for the program).
Execution Status Click on this hyperlink to see the current status of each observation in the program.
Data Taken The UT date(s) on which data were taken.
Completion Status This shows an estimate of the fraction of allocated time that has been used. Note that this is a preliminary estimate and is only an indication of the completion state of the program. The completion state may not reflect the formal time accounting. Also note that some programs may be completed in less than the allocated time (e.g. if conditions were better than requested or if the request was overestimated).

The assigned support staff (Gemini Contact Scientists and National Office staff) for each Gemini North ODB and Gemini South ODB program are listed in the interactive 'snapshots' of the Observing Database (ODB).

GN Director's Discretionary Time Queue Band 1
Ref # PI Partner Title Instrument Hours
allocated
GN-2015A-DD-1 Lopez-Morales Atmospheric Observations of the Super-Earth 55 Cnc e GMOS 4.50
Execution Status: complete Dates Taken:
20150124 20150201 20150217 20150220 20150226 20150227 20150306 20150318
Completion Status:
100%
GN-2015A-DD-2 Daemgen Imaging follow-up of two planetary-mass companion candidates in Taurus NIRI+Altair 2.40
Execution Status: complete Dates Taken:
20150322 20150323 20150324
Completion Status:
100%
GN-2015A-DD-3 Schirmer Quasar ionization echos - completing optical imaging of Chandra sources GMOS 2.20
Execution Status: complete Dates Taken:
20150410
Completion Status:
100%
GN-2015A-DD-4 Ryder Spectroscopic Confirmation of 2 Supernovae Found with GeMS/GSAOI GNIRS 2.60
Execution Status: complete Dates Taken:
20150504 20150505 20150508 20150523
Completion Status:
100%
GN-2015A-DD-5 Trujillo Distant Solar System Objects GMOS / GMOS-S 4.70
Execution Status: complete Dates Taken:
20150611 20150612 20150620 20150621
Completion Status:
100%
GN-2015A-DD-6 Mason The nuclear environment of the least luminous Seyfert galaxy GMOS 1.20
Execution Status: complete Dates Taken:
20150613 20150615
Completion Status:
100%
GN-2015A-DD-7 McDonald The First Map of 10^6K Gas in an External Galaxy - Testing Cooling Flows and Quenching in Galaxy Clusters GMOS 5.00
Execution Status: complete Dates Taken:
20150629 20150702 20150707 20150721 20150807 20150808 20150809
Completion Status:
100%
GN-2015A-DD-8 Kilic Confirmation of a Type Ia supernova progenitor GMOS 3.30
Execution Status: complete Dates Taken:
20150704 20150707 20150710 20150725
Completion Status:
100%
GN-2015A-DD-9 Rupke Deep Spectroscopy of Nearby Galactic Winds GMOS / GMOS-S 8.00
Execution Status: complete Dates Taken:
20150710 20150722 20150723 20150727
Completion Status:
100%
GN-2015A-DD-10 Chapman SMGs and the IGM: Precise GNIRS redshifts for z~2.3 SMGs near QSO sightlines GNIRS 12.00
Execution Status: complete Dates Taken:
20150723 20150724 20150725 20150726 20150727 20150802
Completion Status:
100%

 

[Science Operations home] [schedules home]


Last updated on: 7 Jun 2021 17:29:30 GMT