Gemini South Semester 2016A
The semester calendar shows multi-instrument queue nights, priority visitor nights, scheduled classical runs and engineering or commissioning blocks.
Horizontal rows represent instrument ports, color-coded to indicate instruments mounted.  Instruments are available for science unless otherwise noted.  
Note: ToO PIs should always check the "what's available now" pages that are linked from the contents list for the most up-to-date information. 
Scheduled classical runs are indicated by the last characters of the program ID, e.g., "C-1", whilst Priority Visitor programs are indicated with "PV".   
Engineering or commissioning blocks are shown across all rows when no backup queue is available (or telescope is closed).  
New and full moon dates are shown on the left and indicated in yellow and grey on the dates lines.  Dates above each month are color-coded to show weekends and holidays in red.
Key: GMOS   F-2   visiting instr   Canopus   GSAOI   GPI   Cal unit  
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29      
February Port 1 - up GPI                   GSAOI     GeMS   GT GT C-1   GPI   GPI campaign       February
8 new Moon Port 2 cal                                                         8 new
22 full Moon Port 3 GMOS                 PV: LP-1                                   22 full
  Port 4 Canopus                                                        
  Port 5 F2                                                              
  1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
March Port 1 - up GPI                           GPI campaign           PV: LP-6               March
8 new Moon Port 2 cal                                                             8 new
23 full Moon Port 3 GMOS PV: Q-7                                               Korean time   23 full
  Port 4 Canopus                                                            
  Port 5 F2                                                     Korean time    
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30  
April Port 1 - up GPI             GSAOI   GeMS LP-2     through to   LP2 Kr GT GPI   GPI campaign         April
7 new Moon Port 2 cal                                                           7 new
22 full Moon Port 3 GMOS                                                         22 full
  Port 4 Canopus                                                          
  Port 5 F2                                                              
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
May Port 1 - up GPI                                       PV: Q-36   GPI campaign           May
6 new Moon Port 2 cal                                                             6 new
21 full Moon Port 3 GMOS                                                       PV: LP-8 21 full
  Port 4 Canopus                                                            
  Port 5     Flamingos-2 maintenance         PHOENIX                   Flamingos-2 maintenance     F2    
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30  
June Port 1 - up GPI         GSAOI         GeMS     C-1       GPI                     June
4 new Moon Port 2 cal                                                           4 new
20 full Moon Port 3 GMOS PV: LP-8       PV: LP-1                                             20 full
  Port 4 Canopus                                                          
  Port 5 F2                                 DSSI                          
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
July Port 1 - up GPI         GPI maintenance GPI maintenance GPI maintenance July
4 new Moon Port 2 cal                                                             4 new
19 full Moon Port 3 GMOS         Korean time                                             19 full
  Port 4 Canopus                                                            
  Port 5 F2                                                              