- PIO
- Sciops
- Gemini Home
- Telescopes and Sites
- Science Visitors at Gemini
- Observing With Gemini
- Instruments
- NORTH
- ALTAIR
- GMOS
- GNIRS
- NIFS
- NIRI
- SOUTH
- FLAMINGOS-2
- GeMS
- GMOS
- GPI
- GSAOI
- NICI
- VISITING
- Visiting Instrument Policy
- DSSI Speckle Camera (North)
- TEXES (North)
- RESOURCES
- Integration Time Calculators
- Adaptive Optics
- GCAL
- Magnitudes and Fluxes
- Near-IR Resources
- Mid-IR Resources
- Observing Condition Constraints
- Performance Monitoring
- SV/Demo Science
- Future Instrumentation
- Queue and Schedules
- Data and Results
- Helpdesk
- Statistics
Change page style:
GeMS News
| 26th of December to 1st of January 2013 | Last GeMS run of 2012 - Starting some SV |
|
During the very last run of 2012, we have been able to start some of the SV observations. Among others, a very nice field was observed: the Orion bullets. Check the following press release for all the details:http://www.gemini.edu/node/11925 |
||
| November 2012 to December 2012 | GeMS back on sky: objective ends of commissioning |
|
Between November and December 2012, GeMS will be working on sky, for 4 commissioning runs. These runs will be the lasts one to finish commissioning, and start the transitions toward System Verification and operations for 13A. First runs are dedicated to the Laser Guide Star Facility, while the next runs are dedicated to performance optimizations, stabilization, and GSAOI science commissioning. |
||
| 1st June 2012 - 1st November 2012 | GeMS winter shutdown |
|
For the second year, GeMS will be in winter shutdown for the period June to November. This shutdown aims at fixing and upgrading sub-systems, based on experience gathered on-sky. On the menu for this year: automation of motors on the laser bench, re-alignment of the laser bench, changing motors on the BTO, commissioning of new beam splitters in Canopus, full re-alignment of the Laser Guide Star WFS, potential upgrade for the Natural Guide Star WFS, and transmission measurement and cleaning of all optics ! |
||
| 20 Mar. 2012 | Call for community commissioning targets |
|
See the following call for a first opportunity to use GeMS/GSAOI. See: http://www.gemini.edu/node/11800 For all the details |
||
| 8-15 Mar. 2012 | 10th commissioning run: GeMS with GMOS-S |
|
Due to issues with the cooling of GSAOI, we used GeMS with GMOS. Although the combination of GMOS and GeMS is not intended to be offered as a standard mode in the immediate future, this image is useful for commissioning/verification purposes and demonstrates the capabilities of GeMS over a broad spectral range. It also hints at what is possible with a ground-layer adaptive optics system. Good performance were obtained, with Full Width Half Max (FWHM) of as good as 0.08 arcsec in i-band. |
||
| 12-20 Dic. 2011 | 7th commissioning run: GeMS is working ! |
|
This was (so far) the best run we had. The main goal of this run was to demonstrate that GeMS is working, and it is working well. See: http://www.gemini.edu/node/11715 For all the details | ||
| 9-15 Nov. 2011 | 6th commissioning run. |
|
Back on sky for this 6th commissioning run. Goal is to check that
everything that was working is still working, and that the new upgrades
from the shutdown are operational.
|
||
| 7&8 Nov. 2011 | Canopus & GSAOI are respectively back at the telescope |
|
After a five-month marathon or hard engineering work on both instruments, they are back at the telescope on schedule. The Fast-Steering Array (FSA) has been fully re-designed, re-constructed and re-implemented In summary it has been a very intense period during which many activities were orchestrated in parallel, and which eventually result in a more reliable and better performing system.
|
||
| 1st Jun. 2011 | Planned five-month rework period |
|
In early June 2011, GeMS entered a planned five-month rework period and the 10th of June, Canopus was removed from the telescope and installed in the instrument lab of Cerro Pachon. This shutdown was planned to perform upgrades of subpackages that were deliberately put aside when we decided to go on the telescope end of last year. It also appeared to be the perfect opportunity to fix, repair and upgrade many systems based on the experience that was acquired on-sky, taking advantage of the winter time in Chile less favorable to AO observations. GeMS is scheduled to be back at the telescope on November.
|
||
| 16-22 May. 2011 | 5th and last commissioning |
|
5th and last commissioning of this first period. Unfortunatly it was a difficult commissioning run, extract from the GeMS blog: Autopsy of a run - on May 24, 2011 2:39 PM
|
||
| 15-21 April. 2011 | 4th commissioning run of 2011 |
|
4th commissioning run of 2011: when everything starts to work together and the first image came out of GeMS ! Here is the status of the system during this recording: What is that exactly and what can I see? More info here
|
|
|
| 21-27 March. 2011 | Starting the 3rd commissioning run |
|
Starting the 3rd commissioning run: goals are to finish all the LGSF functionalities and start the Canopus commissioning. "Very good progress tonight. We went throught a lot of offloads debugging, and closing loops. For more info you can download a special Gemini Focus (March 2011)
|
|
|
| 20-26 Feb. 2011 | Starting the 2nd run of the Laser Guide Star facility (LGSF) / GeMS commissioning. |
|
Lot of progress has been done in the BTO control, constellation alignement and more propagation at Zenith and outside Zenith. Extract from Canopus blog: We did it!
|
||
| 22 Jan. 2011 | First laser propagation |
|
"In the early morning of January 22, 2011 at 4:38am, Chile Summer Time, a new era in high-resolution astronomy began with the successful propagation of a 5-star sodium laser guide star "constellation" in the skies over Cerro Pachon in Chile." More details can be found at the following link: http://www.gemini.edu/node/11603
|
|
|
| 10 Jan. 2011 | Canopus installation on the Telescope |
|
On Monday 10th of January, Canopus was installed on telescope. On the 11th, power was turned on. Canopus will now be characterized in this new environment for around 2months, before starting the night time commissioning
|
|
|
| 25 Nov. 2010 | Laser high power spec achieves in LSE. |
|
Vincent Fesquet and LMCT Laser engineer Zach Prezkuta have just spent 3 weeks of nearly non stop work in the laser Service Enclosure to bring the GS Laser back to its preshipment performance level. They succeeded pretty nicely, achieving between 50 to 60W most days during the last week and close to 65W on the day when Zach left back to Colorado. Wavelength locking was achieved a few days earlier. Other performance parameters such as beam quality and stability will be assessed over the next couple of weeks.
|
|
|
| 19 Nov. 2010 | Canopus Transport to Cerro Pachon and installation in the instrument lab. |
|
Canopus was transported from the lab in la Serena base facility to the instrument lab at the telescope in cerro Pachon. The preparation, packing and transportation took 3 days of work for a team of more than 10 engineers and technician. The transport went smoothly, and Canopus is now installed in the instrument lab, where it will be tested before its installation on the Telescope planned for the 10th of January.
|
|
|
| 14 Jul. 2010 | GS laser installation on telescope |
|
The GS laser passed its last Software reliability acceptance test last week and was officially accepted on Friday July 9, 2010. Preparations had been made so that the laser could be installed on the telescope immediately thereafter. Prep work at the summit occurred on Mon-Tue July 12-13 for the Laser Bench Enclosure (LBE) and Laser Electronic Enclosure (LEE) to be transported from the Pachon Instrument Lab clean room to the telescope and installed in their final home: the GS Laser Service Enclosure (LSE). The move took place today, on July 14, 2010, under Mike Sheehan's supervision and with help from a large section of the CP day crew. The move went pretty smoothly. Both the LBE and LEE were installed in the LSE by ~7pm tonight. Look at this podcast for more details.
|
|
|
| 24 Mar, 2010 | Gemini South Laser delivery to Cerro Pachon |
|
The GS laser arrived at 1pm today on the summit. All crates were offloaded by 2:30pm, and stored on the first floor where we will pick them up again on Monday for installation in the instrument lab. Everything went by the book.
|
|
|