Status and Availability

 

Update June 19, 2014

    We observed an erratic behaviour in the decker wheel of Flamingos-2 during last week. The mechanism failed completely during troubleshooting checks on June 17. We are planning to start a 2 week long shutdown of Flamingos-2 in order to fix this mechanism. The work will start by Monday 23rd. In the meantime, the instrument can only be used in imaging mode.

Update May 22, 2014

    After the remediation work performed on the Flamingos-2 camera, its image quality has greatly improved. It now delivers a failry constant fwhm (~ 0.36 arcsec) across its field of view. Spectroscopy is still an issue: a chromatic aberration is affecting the spectral resolution significantly toward the edges of the spectrum. Optical modelling will be needed to first understand this effect and next to plan how to solve it. In the meantime, Flamingos-2 is back on the telescope for science observations.

    The next step is to fully commision the OIWFS. At this time, the OIWFS can be used to guide and provide focus and tip/tilt corrections. However, the OIWFS can not provide reliable astigmatism corrections. We are planning to check the OIWFS performance on the sky within the next week. After that we plan to offer the OIWFS (limited to focus and tip/tilt corrections) for imaging and spectroscopic observations. As soon as the availability of resources and the weather cooperate, we plan to complete the OIWFS commissioining.

Update March 25, 2014

    At present, Gemini plans to have both GPI and GEMs installed on the telescope. As a result, Flamingos-2 will need to be taken out the telescope. We are using this opportunity to perform a remediation work of the camera. At the end of this work we expect to at least understand why the image quality of the instrument is not meeting the specifications. Our plan includes enough time to allow us to fix the camera optics if we are able to quickly diagnose the reason for the current image quality. The plan contemplates to go back on ths sky by May 20th.

    During the week of March 10th we discovered a problem with the OIWFS. Some of the SDSU controller boards have been damaged by condensation during the summer. Several boards have been replaced and the OIWFS is being checked. We expect to re-start the OIWFS commissioning work once we are back on the sky by May 20th.

Update January 17, 2014

    The OIWFS has not been offered yet. We plan to commission it during February. We suggest 2014A PIs with targets early in the semester plan to guide with the PWFS2 instead.

    Please be aware that Flamingos-2 is scheduled to be off the telescope by March 11th. It will be installed back by May 20th. So please plan to prioritize your targets accordingly.

    We have implemented a mid-term solution to the Lyot wheel problem. The initial temporal solution worked well but added some overhead to the observations. This is no longer the case. However, we would like to suggest to the PIs to notify us if they think that the throughput is different than what they would expect.

    We are in the process of acquiring a new K filter that will extend to 2.5microns. This filter would be used with the R3K filter in the near future (14B).

    Finally, work is underway trying to identify the physical mechanism that has caused the camera IQ degradation. Once we identify the reason we will propose a plan for fixing it. In this way, we can recover the original spectral resolution and also start the commissioning of the MOS mode.

Update October 23, 2013

    On the night of October 14th, we discovered a sudden drop in flux from GCAL flats and arcs (as much as 90%). We have tracked down this issue to the fact that any motion of any of the two filter wheels could potentially drag the Lyot wheel. So it is possible that observations might have been vignetted (some 10% - 30%) by the Lyot wheel. The vignetting should not have been more severe than this or else we would have detected it in the GCAL flats and arcs. At this point, we have a temporary work around that allows us to continue observations without affecting the quality of the data.

    We have made a preliminary assessment of the possible vignetting for the programs observed so far. In the next few days, we will notify the PIs of our findings. In the meantime, we suggest PIs to check the the GCAL flats and arcs. These calibrations are always taken either before or after the on-sky data and without needing to move the filter wheels. Therefore, they can be used to determine if there is an unexpected drop in throughput in the on-the-sky observations. In the following GCAL Flats and Arcs link , we provide plots for GCAL flats obtained under nominal conditions (no vignetting).

Update September 5, 2013

    During the last on-sky checks of FLAMINGOS-2 on the night of August 24th we detected an alignment problem with the On-Instrument Wave Front Sensor (OIWFS). The mechanism was inspected this week without significantly disassembling the optics. Unfortunately, we were not able to identify the opto-mechanical cause of the misalignment. In the interest of getting F2 back into operations quickly and given the possibility of using the Peripheral Wave-Front Sensor (PWFS2) as a back up, it was decided to re-align the mechanism as best as it was possible in this short time. A more detailed analysis has been postponed for a later time when we can assign enough resources and better plan for this task.

    The PIs who could be directly affected by this issue are being notified by email. PIs with spectroscopic observations will have a choice to schedule their observations starting next week with the PWFS2 or waiting for us to get the OIWFS ready for sky observations later this month. We suggest that PIs with imaging observations wait until we can test the OIWFS before switching their programs to use the PWFS2.

Update August 5, 2013

    Last week we completed the last commissioning run of 2013A. We had a mix of very good and bad weather. We made good use of the good weather and left the instrument almost ready to start queue observations. This is a list of the main work done during the commissioning run.

  • We completed the commissoning of the imaging mode. We verified that under excelent and stable natural seeing conditions (fwhm in K ~ 0.35 arcsec) the instrument delivers the IQ performance obtained in the lab. Note that this includes degradation of image quality at the edge of the field. We also obtained new photometric observations that will allow us to update the throughput measurements for the instrument. The change is very small ~ 2%.

  • We obtained spectrophotometric observations that will allow us to verify the throughput for the spectroscopy mode. Moreover, we will also derive new models for the ITC that will be uploaded for the next observing season.

  • We completed the commissioning of the 2-pix slit for different types of objects and instrument settings.

  • We have derived new GCAL and comparison arc calibration tables that will be updated on the OT smartcal tables in time for the next ODB release. We will also upload them on the web.

  • We have also analyzed data that suggests that spectroscopic GCAL flats and arcs should be taken at night. Also we suggest taking night time calibrations for every one hour of observations. We will update the public webpages and the ODB with this info shortly.

  • The on-instrument wavefront sensor (OIWFS) fast guiding is not currently delivering optimal corrections, due in part to a hardware problem with the OIWFS electronics. Work continues to correct this problem. The impact on IQ=85 percentile observations is not critical, but it does affect performance under better (IQ=20% and IQ=70%) conditions.

Update July 5, 2013

    Last week we completed the most recent commissioning run. As we expect this time of the year, the weather did not cooperate and we had a mix of poor seeing and clouds. So we concentrated on commissioning the longslit spectroscopic mode and tuning the active optics corrections of the OIWFS. The instrument performed very well during this run without any issues. The following is a summary of the work done during the run.

  • We obtained R3K + J, H, and Ks long-slit (3-pix slit) spectroscopy of extended objects. These observations were used to check the performance of the refurnished R3K grism that suffered some damage earlier this year. See below the 2-d spectrum of the galaxy NGC 253 obtained with the R3K + Ks.

  • We continue the work on the OIWFS. The OIWFS is used to provide focus, tip-tilt, and astigmatism corrections. The focus and tip-tilt are performing adequately. The work left consists on tuning the astigmatism corrections that are used to adjust the figure of the primary mirror. This work is ongoing.

  • We obtained out of focus images of an on-axis star in order to verify the alignment of the Lyot stop and to check that there is no vignetting.

Update June 13, 2013

    FLAMINGOS-2 moved another step closer to its final round of commissioning observations when it was moved from the summit instrument lab to the port 5 in the Instrument Support Structure (ISS) of the telescope in June 10th, 2013. For the past month-and-a-half F2 underwent work on the summit of Cerro Pachón to address repeatability problems with the multi-object spectroscopy wheel mechanism. This and other systems checked out successfully, leading to the installation of F2 on the telescope. F2 will start its on-sky commissioning on June 20, 2013.

Update May 6, 2013

    We have just completed the most recent commissioning run with F2. During most of the run we had bad and very bad seeing in the 1 to 4 arcsec interval in Ks. We had a brief period of good seeing (~0.6 in Ks for a couple of hours on the night of 4/29). Overall, we made progress on the commissioning plan taking full advantage of weather conditions that normally would have been considered "weather loss." Unfortunately, the MOS wheel started to behave erratically during the 5th night of the 6 night run. We were able to continue the commissioning by manually moving the MOS wheel to different positions. In addition, we found that the gate valve baffle, used to minimize the internal background, was slightly misaligned.

    We are currently warming up the MOS dewar and check this mechanism to ascertain the nature of this fault and fix it. In parallel, we are also warming up the camera to realign the gate valve baffle in order to carry out the commissioning of faint objects.

    Despite the seeing conditions, we performed several commissioning tasks that could be checked out from the commissioning plan.

  • Fast guide (tip-tilt and focus) with the OIWFS. Note that during the few hours with good seeing we verified that the fast guide with the OIWFS has an acceptable performance under IQ=85%. We have pending the tuning of the AO corrections.

  • Full guiding (fast + AO) with PWFS2.
  • Imaging throughput in all bands

  • Spectroscopic observations of extended objects through the 3-pix slit, 6-pix slit, and 8-pix slits with the JH and HK grisms.

  • Spectroscopy of point sources objects through the 3-pix slit, 6-pix slit, and 8-pix slits with the JH and HK grisms.

  • Measure the flexure between the OIWFS and the focal plane

  • Perform the usual back to the sky calibrations (i.e., IAA, WCS, SF paramenters)

 

 

Update April 2, 2013

 

    FLAMINGOS-2 is undergoing an unscheduled thermal cycle. This was prompted by two recent faults:

  • A previous uncontrolled cool down of the Hawaii-2 detector while powered has created an excessive number of charge traps leading to excessive hot pixels. In addition, the readout noise has changed. We expect to correct these issues with a warm up of the detector to room temperature.

  • The MOS wheel mechanism started to stall. We need to warm up the MOS dewar in order to inspect and fix this mechanism.

  • The expected down time is between two to three weeks. So we still expect to have FLAMINGOS-2 available for the start of its commissioning run at the end of April.

 

 

Update March 21, 2013

  • We have performed an initial assessment of the imaging performance of F2. At the best focus on-axis, we obtain fwhm ~ 0.35 arcsec for pinholes located within a radius < 0.5 arcmin, and fwhm 0.44 arcsec for the region between 2 to 2.5 arcmin. The following plot shows the image quality as a function of radius. We also show, as reference, the limits for the image quality (IQ) constraints of 20%, 70%, and 85%. We are still evaluating the effects of the IQ on spectroscopy mode. Please take these values into consideration for the 13B proposal cycle.

    This plot shows the radial profile of the fwhm for a Ks 2-pix pinhole. We also show the limits for the IQ conditions: 20%, 70%, and 85%.

  • The instrument is now mounted on the flex-rig to undergo further tests. After this, the instrument will be installed on the telescope so that we can start its commissioning in late April 2013.

Update March 1, 2013

  • Extensive re-alignment work has been done on the instrument. At this time, the excessive coma and astigmatism present in the January images has been almost eliminated. However, the current PSF is not yet optimal and we continue to work improving it. We plan one more lab cold cycle in late March before starting the commissioning in April.

  • The R3K grism has been re-installed in the instrument. We have extracted and masked the damaged region of the replica transmission grating. Moreover, we are planning to purchase a new R3K grism in the next months.

Update January 30, 2013

  • The instrument was cooled down in early January 2013 after a 10 month shut down period. During this time, we worked on: modifying the lens holders for the entire camera and the field lens, installing a new field lens, installing a new window cover, installing a new detector board for the current Hawaii-2 detector, re-aligning the OIWFS, improving the thermal shielding of the camera dewar, and performing a first check of the overall optical alignment of the F2 optics (lenses and detector).

  • All mechanisms worked as expected including the Hawaii-2. The mechanisms were exercised and we even performed a limited flexure test that showed no new issues.

  •  

  • One issue that we still have to work on is the overall optical alignment of the camera. The images obtained during this first cool down present excessive coma. We are in the process of improving the alignment so that we can perform new tests during the next cool down in February.
  •  

  • We also discovered some damage on the surface of the grating of the resolution 3000 grism (R3K). The grism cell was removed from the instrument in order to examine it and avoid further damage. We have contacted the vendor and the manufacturer so that they can help us to determine the reason for the damage. Then, we will decide what steps to take in order to be able to have a R3K grism available as soon as possible.

Update September 12, 2012

  • A new cell holder for the Collimator lens (L1) has been received at Cerro Pachon. The thermal properties of this new cell holder will be tested by installing the original, broken lens within it (the lens will be glued). After this baseline test, a set of tests will be carried out with the new holder and the new L1. The new L1 lens arrived at Cerro Pachon in mid-August.

  • During the shutdown, stresses in other lenses, located in the camera, have been uncovered. These stresses are consistent with point contact on the radial rods due to tilt arising from decentering during cool-down. Two of these lenses are being replaced. In order to minimize the risk of another lens fracture, the way all the camera lenses are held will be modified. The required modifications are minimal and are aimed solely at reducing stress without incurring additional delay. They will be implemented while the new L1 assembly is tested and the OIWFS is realigned in the MOS dewar.

  • We remain on schedule to be on the sky no later than mid March 2013.

Update August 9, 2012

 

  • As a result of the KP root cause analysis, Gemini has designed a different setup to hold L1. Several thermal cycles were performed on the MOS dewar in order to understand the temperature behaviour of the L1 lens and its holder. For this, we used the original L1 lens holder and a "glued" L1 lens fitted with temperature sensors. Moreover, we contracted Quartus Engineering to perform a FEA of the original L1 lens holder under warm, cold, and thermal changing conditions (i.e., thermal cycles of the MOS dewar needed for mask changes). The new design has been revised by internal and external experts including Quartus Engineering. This new design incorporates the lessons learned from the FEA and the results of the thermal cycles tests. The main feature of the new design is a dramatic reduction on the mechanical stress experienced by the L1 lens under all operational conditions. The new design will recycle the current hardware but change the way the lens is supported radially and axially. This new holder is now ready to go in fabrication.

  • A new L1 Calcium Fluoride was received at Gemini South on July 11 and a spare is expected to ship from another vendor by the end of July. Those lenses have their sides polished to decrease the internal stress left over by the fabrication process.
  • A new Hawaii-2 fan out board has been installed and tested. This new board includes some improvements designed to minimize the risk of possible delamination and improve the thermal control of the detector.

Update April 9, 2012

Our Kepner-Tregoe root-cause analysis concluded that the fracture was not caused by a single factor but by several possible factors across time. Based on all our observations, measurement of the as-built assembly of the lens and mount, and the workmanship of some critical surfaces in contact, the tensile stress is large, which leaves little margin to any process deviations that could occur over time. Based on this and in order to improve the long term robustness of F2 we have decided to:

  • Build a new L1 cell with a stress reducing design.
  • Retrofit this design if possible for the other lenses.
  • Polish the new L1 lens edge to relieve internal manufacturing stress.
  • Review and improve the cool-down and warm up processes to avoid future occurrences of the problem.

 

 

Update March 12, 2012

Collimator Lens Crack

On February 3rd, while doing routine tests, we discovered what appeared to be vignetting in the FOV (see below). Further inspection revealed the cause to be a major crack in the large collimator lens ("L1").

Figure 1 (left) Diagram showing the location of the collimator lens. (right) K band image showing the apparent vignetting covering half the FOV. The windmill pattern visible is produced by the window cover shutter.

 

Figure 2. This is the cracked lens. By the time the instrument had been warmed up, the crack had propagated across the entire diameter.

Ongoing Work

 

In order to expedite the return of F2 to its commissioning phase, we are pursuing the following actions:

  • Two replacement collimator lenses have been ordered, from two different vendors.
  • A new lens holder is being designed. We are consulting with internal and external experts in order to validate this new design.
  • We continue our analysis of the root cause of the lens failure. Based on our measurements of the size of all as-built parts and forces of the springs, our preliminary analysis focused on calculating the tensile stresses created on the lens at the contact points of the two radial defining rods (see the figure below from a report by G. Perez at Gemini Observatory).We find that the analytical calculated tensile stress on the glass is over 5000 lb/in2.

 

 

 

 

The picture above shows the lens inside the lens holder prior to disassemble (compare with the previous diagram). The bottom picture shows the location of the radial defining rod and the crack in the lens.

 

Because of the uncertainty in the planned schedule to get back on the sky, we are not able to offer F2 for regular use during 2012B. Nonetheless, we are working toward making the instrument available to the science community as soon as possible. If we maintain this initial schedule, we anticipate expanding the System Verification phase to maximize the earliest opportunities for science.

Our planned schedule indicates that the Expected Time1 for F2 to be ready for its recommissioning is October 1, 2012. With the following boundaries:

Optimistic time: July 28, 2012

Most likely time September 10, 2012

Pessimistic time December 5, 2012

1According to PERT (Program Evaluation and Review Technique) the Expected time = ( Optimistic + 4 x Most likely + Pessimistic ) / 6

 

Please check this page periodically for frequent updates about FLAMINGOS-2.

Last update 03/12/2012